Superior Courts Act, 2013
R 385
Mine Health and Safety Act, 1996 (Act No. 29 of 1996)Guideline for a Mandatory Code of PracticeRoad and Rail Safety Management in the South African Mining IndustryPart C: Format and Content of the Mandatory COP10. Level crossing management10.3. Design of level crossings |
| 10.3.1. | The COP must outline how the network operator, in collaboration with the private road owner or road authority must design new and/or modify level crossings. |
| 10.3.2. | This design process must incorporate the concept phase studies and results of the level crossing physical assessment (clause 15, SANS 3000 2-2-1). The process must include and confirm the following: |
| (a) | Current and future train patterns and volumes (inclusive of mixed rail traffic). |
| (b) | The classification and ownership of the road. |
| (c) | The type of road traffic, patterns and volumes. |
| (d) | The road geometry. |
| (e) | Stopping sight distance for vehicles. |
| (f) | The line of sight for pedestrians, road vehicle drivers and train drivers. |
| (g) | The rail network geometry. |
| h) | The rail traffic patterns and volumes, such as: |
| i. | The train operating parameters including bi-directional traffic. |
| ii. | Train lengths. |
| iii. | The section speed. |
| iv. | The location of a level crossing (service lines, yards, sidings, etc.). |
| (i) | Unrestricted and safe movement of trains, road vehicles and public usage during peak and off-peak hours. |
| (j) | Unrestricted and safe movement of trains, road vehicles and public during normal, abnormal and degraded operations as defined in the relevant part(s) of SANS 3000 or emergency conditions. |
| (k) | Provision for persons with disabilities including persons with reduced mobility, visual or audio impairment. |
| (l) | The train and road network operating parameters including provision for bi-directional traffic or 'wrong road' working, or both. |
| (m) | Current and future train speed. |
| (n) | The number of interacting train movements. |
| (o) | The speed, mass, acceleration and brake performance of trains. |
| (p) | The provision of suitable monitoring and closed-circuit television equipment at all relevant new level crossing(s), modified or existing level crossing(s), or a combination thereof, and pedestrian crossings. |