24. Decision on S&EIR application

 

(1) The competent authority must within 107 days of receipt of the environmental impact assessment  report and EMPr, in writing—

[Words preceding regulation 24(1)(a) substituted by Notice No. 326 of 2017]

(a) grant environmental authorisation in respect of all or part of the activity applied for; or
(b) refuse environmental authorisation.

 

(2) To the extent that authorisation is granted for an alternative, such alternative must for the purposes of subregulation (1) be regarded as having been applied for, consulted on and its impacts investigated.

 

(3) On having reached a decision, the competent authority must comply with regulation 4(1), after which an applicant must comply with regulation 4(2).

 

(4) The Minister responsible for Mineral Resources may only issue an authorisation if the provisions of section 24P(1) of the Act have been complied with.

[Regulation 24(4) substituted by Notice No. 326 of 2017]