Acts Online
GT Shield

Conservation of Agricultural Resources Act, 1983 (Act No. 43 of 1983)

Regulations

Soil Conservation Scheme

8. Requirements for payment of subsidies

 

A subsidy may be paid to a land user in terms of this scheme in respect of the construction of a soil conservation work if—

 

(a) that land user is the owner of the farm unit on which such soil conservation work has been constructed;

 

(b) the farm unit on which such soil conservation work has been constructed—
(i) is situated within the area referred to in section 4; and
(ii) has been entered for participation in this scheme in terms of section 10 or is deemed to have been thus entered;

 

(c) such soil conservation work has been classified in terms of section 6 as a protection work, a drainage work, a veld utilisation work or a drought relief work;

 

(d) the construction of such soil conservation work has been indicated as a proposed work in the list of soil conservation works forming part of the farm plan for the farm unit concerned;

 

(e) a consent for the construction of such soil conservation work has been issued in terms of section 12 or is deemed to have been thus issued;

 

(f) a notice of the completion of such soil conservation work has been furnished in terms of section 13 or is deemed to have been thus furnished;

 

(g) such soil conservation work has been constructed corresponds with the approximate position thereof as indicated on the map forming part of the farm plan for the farm unit concerned;

 

(h) the dimensions and specifications of such soil conservation work correspond with the plans and specifications that accompanied the relevant consent referred to in section 12 or have been accepted in terms of that section;

 

(i) a statement or report on such soil conservation work has been made or compiled in terms of section 15 or is deemed to have been thus made or compiled;

 

(j) such statement or report has been accepted by the executive officer in terms of section 16, and money appropriated for the purposes of this scheme are available; and

 

(k) all the other provisions of this scheme with regard to such soil conservation work and the farm unit on which it has been constructed have been complied with.