Acts Online
GT Shield

Electricity Regulation Act, 2006 (Act No. 4 of 2006)

Regulations

Electricity Regulations on New Generation Capacity, 2011

12. Transitional provisions

 

( 1) The provisions of these Regulations do not apply in the case of any project relating to the electricity generation capacity listed under "Current Programmes" in the table titled IRP 1 in Schedule A to GN 25 of 29 January 2010: Determination regarding the integrated resource plan and new generation capacity, save for the electricity generation capacity listed as REFIT.

 

(2) Notwithstanding subregulation (1), regulation 10 shall apply to the Peaker Project.