Construction of a petroleum loading facility (PPL.lf.F1)

 

 

Provide the following information/documentation. Each numbered item below should be copied and appear at the top of a page with your information below.

 

1. A technical description of the proposed loading facility to be constructed, including:
(a) GPS Coordinates;
(b) the number of loading points;
(c) type of each loading point (e.g. loading arms or flexible hose);
(d) details of the proposed auxiliary pipeline/s including:
(i) diameters;
(ii) lengths;
(iii) the storage facility to be connected to; and
(iv) receipts and delivery points

 

2. Maps and diagrams where appropriate.

 

3. Details of capacities at the various stages of development, planned and potential receipt and delivery points.

 

4. The rate at which petroleum can be conveyed through the loading facility and the time necessary for ships to be brought into position for loading, and the dimensions and capacities of any auxiliary pipelines connected thereto.

 

3. Copy of the agreement or authorisation from the National Ports Authority permitting the construction of the facility on its property, where appropriate.

 

4. In the case of greenfield projects, for which a licence is sought, information on the economic, market and financial forecasts and other relevant information upon which the proposed project for the licence applied for is based.

 

5. Provide information required in terms of rules 12(7) and 12 (8) of these Rules.

 

6. A copy of the proposed emergency plan contemplated in section 20(1) (x) of the Act.

 

7. A copy of the intended loading facility operational procedures.

 

8. Status in terms of the National Key Points Act, 1980 (Act No.102 of 1980).

 

9. Details of proposed security arrangements.

 

10. Details of the development programme including:
(a) planned capacity of the loading facility project during the various stages of development;
(b) the schedule of implementation and minimum investment commitments for the development programme; and
(c) the deadline to commence service for each stage contemplated.